Joined Companies

 

Work Locations & Experience Summery

 

 

Aug 2001 to Present :

country: Qatar

 

Company: - Al Jaber Engineering L.L.C., Qatar

Position: - Projects Manager / Senior Project Manager

 

In Aug 2001 I have joined Al Jaber Engineering in a position of Projects Manager /Head of Construction Department.

 

Report to: - The Managing Director

 

June '07 - Present :

country: Qatar

 

Dubai Towers - Doha Project

Client: - Sama Dubai

Position: - Senior Project Manager

 

Report to: - Al Jaber Managing Director and Al Habtoor Project Director

The Dubai Towers – Doha Project, is a Joint Venture Project; which is awarded to, Al Jaber Engineering Co. and Al Habtoor Engineering.

 

March 06 - June 07:

country: Qatar

 

Dubai Towers – Doha Project  

Enabling works package project

Client: - Sama Dubai

Position: - Project Manager

 

Aug 2001 – March 06 :

country: Qatar

 

Company: - Al Jaber Engineering L.L.C., Qatar

Position: - Projects manager /Head of Construction department

Managed multiple large and small projects, such as the following;

 

1- Project: - Hamad medical city surface & ground water scheme.

Client:  Ashgal

 

2. Water supply to motor cycle race track

Client: - KAHRAMMA

 

3.Excavation and Removal of Rubbish Tip for New Doha International Airport

Client: - Steering Committee New Doha International Airport

Overseas Bechtel, Incorporated (OBI)

 

4. Doha 2006 Asian Games Village Underpass and Access Road

Client: - Public Works Authority

 

5. EPC Lump Sum Contract for Store Building ‘F’

Client: - Qatar Fertilizer Co. (QAFCO)

 

6. EPC of a New Office Building at Ras Laffan Site for Ras Gas

Client: - Ras Laffan Liquefied Natural Gas Co.

 

7. Procurement & Construction of Al Waha Club At Al Khore

Client: - Ras Laffan Liquefied Natural Gas Co. (Ras Gas)

 

8. GTC 15/2002 and GTC 16/2002.

Client: KAHRAMAA

 

9.GTC 102/MIC/03:

Client: Qatar Petroleum

 

10. DRC 0098 

Return effluent Scheme – Distribution Mains T6 to T7 Civil Project 646.

Client:  Ashgal

 

11. EPC of Ras Laffan waste treatment facility

Client: Ras Laffan Liquefied Natural Gas Co. (Ras Gas)

 

in addition to many infrastructure projects.

 

September 2000 - August 2001:

country: Jordan

 

Company: - MID Contracting, Jordan

Position: - Project Manager

 

May 1998 - August 2000:

country: Saudi Arabia

 

Company: - Al Mobty contracting, Saudi Arabia

Position: - Project Manager

 

Sep 1997 - May 1998:

 country: Saudi Arabia

 

Company: - Al Redwan Co., KSA.

Position: - Quality Control Manager

 

Jun 1991 - Aug 1997:

 country: Jordan

 

Company: - MID Contracting, Amman - Jordan.

Position: - Project Manager

 

Nov 1987 – Jan 1991:

country: Qatar

 

Company; - khalifa bin Khalid trading and contracting

Doha, Qatar

Position: - business manager

Type of business

International trading of building materials

Drill of deep water wells and construction of private housing compounds.

 

July 1984 – OCT 1987:

country: Jordan

 

Position: - site engineer

Projects; -  al jafer and al azraq highway

Rehab & nuaymeh highway                       

Road works, Bridges

 

March 1982 - Aug1983:

country: Jordan

 

Position: - trainee site engineer

Company; - George wimpy international

Project; - Ein al bash water reservoir

 

March 1981 – Aug 1982:

country: Jordan

 

Position: - trainee site engineer

Company; - John Laings international

Projects; - Jordan armour rebuild facilities