Projects on Progress

 

Aug 2001 to Present


Company: -Al Jaber Engineering L.L.C., Qatar

Position: - Projects Manager / Senior Project Manager

In Aug 2001 I have joined Al Jaber Engineering in a position of Projects Manager /Head of Construction Department. Charted an impressive career graph;

Report to: - The Managing Director.

 

Responsibilities:

  • To manage multiple large and small projects.

  • Direct, oversee, monitor and evaluate the activities of all project managers, purview their performance, and training.

  • Review projects constructability, scopes of work, sub-contracting, procurement and scheduling.

  • Coordinate all processes and functions with project managers, planners, and quantity surveyors.

  • Perform contract administration, to illustrate Prepare progress reports, formulate and negotiate claims, counter claims and contractual correspondences based on FIDIC.

  • Manage due diligence requirements and liaising with governmental institutions to acquire necessary permits.

  • Formulate construction strategies and synchronize project activities in coordination with project budgets.

  • Participate in the development of company industry standards, such as, environmental, operational cost, and capital improvement objectives.

 

Aug 2007 to Present

 

Dubai Towers - Doha Project

Client: -Sama Dubai

Position: - Senior Project Manager

Report to: - Al Jaber Managing Director and Al Habtoor Project Director

 

The Dubai Towers Doha Project, is a Joint Venture Project; which is awarded to, Al Jaber Engineering Co. and Al Habtoor Engineering. The Project encompasses the construction of 5 basements, GF, GMF and 90 storey building worth over $600 Million.

 

The project plot area is 12500 m2 where as the tower floor area is approximately 2000m2 with a complicated core walls structure and steel framed structure. Total built area of the project is 320,000.m2 and 440m high.

 

Achievements:

  • Attended all co ordinations , preparations, and managed to Cast of tower raft of 15000 m3 of concrete continuous non stop in less than 90 hour

  • Achieve  construction tower core walls cycle of 250 lm in 7 days per floor.

  • VIP speaker in the 2nd annual forum of Global Construction Technologies and building Material .prepared presentation of case study on Dubai towers. for more information visit the clip board at front page of the web.